I am adding tasks for my Project. There are many tasks which have before the current date. But when I try to enter the start date as a previous date, it automatically updates the start date as the current date. Any solutions?

asked 11 Feb '14, 00:04

danish723's gravatar image

danish723
1144
accept rate: 0%

asked 11 Feb '14, 00:04


this does work on firefox, wampserver on win 7 on latest code from git.\n. Maybe you have set tasks to follow dependencies or their parent tasks so they take over those start dates?
permanent link

answered 12 Feb '14, 09:50

opto's gravatar image

opto ♦
82342110131
accept rate: 10%

answered 12 Feb '14, 09:50

Your answer
toggle preview

Follow this question

By Email:

Once you sign in you will be able to subscribe for any updates here

By RSS:

Answers

Answers and Comments

Markdown Basics

  • *italic* or _italic_
  • **bold** or __bold__
  • link:[text](http://url.com/ "title")
  • image?![alt text](/path/img.jpg "title")
  • numbered list: 1. Foo 2. Bar
  • to add a line break simply add two spaces to where you would like the new line to be.
  • basic HTML tags are also supported

Question tags:

×13
×5

question asked: 11 Feb '14, 00:04

question was seen: 377 times

last updated: 12 Feb '14, 09:50

powered by Bitnami OSQA