Hi, I have created a project and created a task under the project. The end date however is not being affected even after the \"save\" button has been clicked. Please is there anything I'm not doing right? Thanks.

asked 08 Sep '14, 13:23

ese7's gravatar image

ese7
022
accept rate: 0%

asked 08 Sep '14, 13:23

The end date of the project or the task?

(08 Sep '14, 23:01) caseydk ♦♦ caseydk's gravatar image

hi keith, remove field by js if milestone is checked??

(09 Sep '14, 01:46) opto ♦ opto's gravatar image

As noted by Opto, a milestone doesn't really have a separate end date. It always has a duration of zero therefore the end date is *always* the same as the start date. I'll look at hiding/disabling the end date box.
permanent link

answered 09 Sep '14, 10:21

caseydk's gravatar image

caseydk ♦♦
742284048
accept rate: 32%

answered 09 Sep '14, 10:21

Thanks Casey

(10 Sep '14, 15:44) ese7 ese7's gravatar image
Your answer
toggle preview

Follow this question

By Email:

Once you sign in you will be able to subscribe for any updates here

By RSS:

Answers

Answers and Comments

Markdown Basics

  • *italic* or _italic_
  • **bold** or __bold__
  • link:[text](http://url.com/ "title")
  • image?![alt text](/path/img.jpg "title")
  • numbered list: 1. Foo 2. Bar
  • to add a line break simply add two spaces to where you would like the new line to be.
  • basic HTML tags are also supported

Question tags:

×13
×5

question asked: 08 Sep '14, 13:23

question was seen: 367 times

last updated: 10 Sep '14, 15:44

powered by Bitnami OSQA